New Builds NEW BUILD 042

Week 38

Click on any of the images below to view in more detail.

Installation of cabling in the engine room continues 

Tying cables into their trays in the engine room 

Spraying polyurethane insulation onto the fish room ceiling 

The finished insulation on the fish room ceiling 

Another view of the finished insulation on the fish room ceiling 

Fitting out the wheelhouse is now being continued 

Starting to fit the framework to the galley and mess area walls 

Later in the week; partitioning off the mess from the galley 

Starting to install the electrics in the mess and galley areas 

The hydraulic actuators waiting to be fitted to the top of the rudder post